26th October 2023 in Construction, Supply Chain
Sofia Offshore Wind Farm and Dogger Bank C, the third phase of Dogger Bank Wind Farm, will begin transporting electricity transformers from Teesport to the home of both projects’ onshore converter station sites near Lazenby from late October into mid-December.
There will be four Sofia deliveries anticipated, starting on the Saturday mornings of 28 October and 4, 11 and 18 November. Each delivery will take approximately one hour, depending on the conditions.
There will also be a series of deliveries to support Dogger Bank C Wind Farm’s converter station construction programme. The transformers will take the same route and commence on 18 November, followed by 25 November and 2 and 9 December.
The transformers will travel from Teesport via the A1015 and A174 and will be delivered on specialist girder frame trailers provided by UK firm Allelys. The size of the transformers requires the use of abnormal load vehicles due to being approximately 35m long and 4.55m wide – with the load travelling at roughly 10 -15 miles per hour.
Chris O’Donnell, Site Manager for DBC Onshore Converter Station said:
“While we will do everything we can to minimise disruption during these deliveries, it is possible some journey times may be slightly longer than normal and we would ask occupants and local residents for their patience as we carry out this critical work.”
“Delivery of these transformers is an important milestone for the construction of our infrastructure in Redcar.”
“We are extremely grateful for the ongoing patience and understanding of the communities in this area as we build the infrastructure that will help the UK to reduce carbon emissions and create a secure electricity supply for 6 million UK homes.”
Matthew Archer, Site Manager for Sofia Onshore Converter Station said:
“Sofia will be RWE’s most state-of-the-art offshore wind farm yet and a major addition to our growing portfolio of renewable energy assets.”
“Work on the station at Wilton continues at pace, and the arrival of these transformers is an important moment for the project.”
“As ever I’d like to thank the local community for their patience. We’re doing our best to keep disruption down to a minimum at all times. In this instance we expect that there may be some minor disruption to the roads linking Teesport to our Wilton site, with some journey times taking a little longer around mid-morning on affected days.”
Sofia and Dogger Bank C’s contractors GE and Hitachi Energy are currently working on the two projects’ respective onshore converter stations (OCS), that will convert electricity from the two offshore wind farms into a current that will go into the national grid network for distribution to homes and businesses.
The projects are both located on Dogger Bank, more than 195 kilometres from the north-east coast of England, with their export cables coming ashore on Teesside, between Redcar and Marske-by-the-Sea.
Sofia is 100% owned by RWE, and Dogger Bank Wind Farm is a joint venture between SSE Renewables, Equinor and Vårgrønn. Although they are owned by different companies, the developers realised early that it made sense to work jointly on their shared cable corridor, with civil engineering works being carried out by J Murphy & Sons (JMS). Sofia is leading the works on behalf of both projects.
If you’d like to know more about either project, please visit: Sofia Offshore Wind Farm or Dogger Bank Wind Farm
We also provide regular updates on our social media channels @DoggerBankWind and @sofiawindfarm
Delivery dates were correct at the date of issue; however they may be subject to potential change at short notice.
ENDS
13th October 2023 in Operations, Project news, Supply Chain
Certex UK’s Great Yarmouth based Engineering Services Division has won a major framework to supply statutory inspection and maintenance services on Dogger Bank Wind Farm.
The contract covers inspection and maintenance of cranes, personnel lifts, general lifting, and safety equipment across all the wind turbines and balance of plant.
Terry Hoenes, Renewables Divisional Manager, Certex UK said: “We have a long-established history working with Equinor on the Greater Wash windfarms off East Anglia and are delighted to have been awarded the 5-year framework. Our hard work over the years providing a strong service and the work put in to produce a competitive tender have paid off and we look forward to starting work on the GE platform wind turbine, the first of its kind in the UK”.
Certex UK Engineering Services Division is part of the Lifting Solutions Group of 22 companies with over 100 locations worldwide, with the renewable energy sector largely being served to date from the UK, Taiwan, and Denmark. However, a newly launched global renewables division incorporates additional companies in Germany, Spain, France, China, and the United States, which has recently pivoted towards wind energy.
Ian Shaw, Engineering Services Divisional Manager, said:
“This is another great step forward for our Engineering Services Division, and working closely with Equinor, gives us the opportunity to introduce more new starters to the industry through our mentorship and training programmes. Equinor has always been an excellent ambassador for development of new starters which helps us to grow a sustainable skilled workforce.” Shaw added “The wider renewables industry growth is continually accelerating, and we need to ensure the supply chain and pool of skilled workers are available, to play our part in this we have developed a route to career programme covering the entry level GWO safety training at our newly accredited facility in Doncaster and the technical inspection training at our site in Great Yarmouth. We have also recently started working with ex forces resettlement agencies and look forward to introducing many more new people to a career in wind”.
10th October 2023 in Construction, Press releases, Project news
- UK Prime Minister Rishi Sunak hails Dogger Bank’s role in bolstering energy security, creating jobs, lowering costs, and achieving Net Zero.
- First power achieved at UK’s Dogger Bank as the first of 277 turbines installed 130km from UK coast.
- Dogger Bank is now connected via HVDC technology to Britain’s national grid and providing renewable power to homes and businesses.
- Each rotation of the first turbine’s 107m long Haliade-X blades can produce enough clean energy to power an average home for two days.
- When complete Dogger Bank will deliver clean energy to six million homes annually.*
The world’s largest offshore wind farm under construction, Dogger Bank, has started producing electricity for the first time for British homes and businesses, marking a major milestone in the development of the offshore wind industry and the transition to a cleaner, more secure energy system.
UK Prime Minister Rishi Sunak has hailed this landmark moment, saying Dogger Bank will bolster energy security, create jobs, lower electricity bills and keep us on track for Net Zero.
The 3.6GW Dogger Bank Wind Farm is being constructed in UK waters 70 nautical miles (130km) off the coast of Yorkshire and in three 1.2GW phases known as Dogger Bank A, B and C. Power from the project’s first offshore wind turbine at Dogger Bank A is now being transmitted to the UK’s national grid via Dogger Bank’s high-voltage direct current (HVDC) transmission system, marking the first-time use of HVDC technology on a UK wind farm.
First power followed the installation of the first of GE Vernova’s ground-breaking Haliade-X 13MW turbines, one of the largest and most powerful globally, at the Dogger Bank site. This is the first time Haliade-X units have been energised offshore anywhere in the world.
Each rotation of the 107m long blades on Dogger Bank’s first operational turbine can produce enough clean energy to power an average British home for two days.
When fully complete, Dogger Bank’s world-record-beating 3.6GW capacity will comprise 277 giant offshore turbines capable of producing enough clean energy to power the equivalent of six million homes annually and deliver yearly CO2 savings equivalent to removing 1.5 million cars from the road*.
UK Prime Minister Rishi Sunak said:
“Offshore wind is critical to generating renewable, efficient energy that can power British homes from British seas.
“I’m proud that this country is already a world leader in reaching Net Zero by 2050, and by doubling down on the new green industries of the future, we’ll get there in a way that’s both pragmatic and ambitious.
“That’s why it’s fantastic to see the world’s largest wind farm, Dogger Bank, generating power for the first time today from UK waters, which will not only bolster our energy security, but create jobs, lower electricity bills and keep us on track for Net Zero.”
Dogger Bank is being developed and built by the UK’s SSE Renewables in a joint venture with Norway’s Equinor and Vårgrønn (a joint venture of Eni Plenitude and HitecVision). SSE Renewables is lead operator for the development and construction of Dogger Bank Wind Farm. Equinor will be lead operator of the wind farm on completion for its expected operational life of around 35 years. Vårgrønn brings specialist offshore wind expertise to the project.
Alistair Phillips-Davies, Chief Executive of SSE, said:
“There’s been lots of talk about the need to build homegrown energy supplies, but we are taking action on a massive scale. Dogger Bank will provide a significant boost to UK energy security, affordability and leadership in tackling climate change. This is exactly how we should be responding to the energy crisis.
“But it is also a landmark moment for the global offshore wind industry, with Dogger Bank demonstrating just what can be achieved when policymakers, investors, industry, and communities work together to achieve something truly remarkable.
“The innovations this pioneering project has developed will also mean future developments can be built faster and more efficiently, accelerating the clean energy transition. Now, of course, the challenge is to accelerate the next wave of these projects and we look forward to working with governments to bring these forward as soon as possible.”
Anders Opedal, CEO of Equinor, said:
“Set against the broader energy context, Dogger Bank, the world’s largest offshore wind farm demonstrates the best of what the offshore wind industry can offer, with innovative technologies, long-term jobs and economic growth and security of electricity supply at a major scale.
“A renewable mega-project like Dogger Bank constitutes an industrial wind hub in the heart of the North Sea, playing a major role in the UK’s ambitions for offshore wind and supporting its net zero ambitions.
“First power from Dogger Bank, is a testament to the collaboration between the authorities, the project partners, suppliers and our host communities to realise this project.”
Olav Hetland, CEO of Vårgrønn, said:
“Dogger Bank’s first power milestone demonstrates that offshore wind is ready to power Europe’s energy transition.
“While today we celebrate Dogger Bank providing its first power, the offshore wind farm is delivering much more than renewable energy. The project has contributed to building industry and creating local jobs and will continue to do so over several decades. Maximising these positive local ripple effects of offshore wind projects is essential to maintaining strong support for offshore wind and the energy transition.
“Looking ahead, we expect the Northeast of England to hold a central place in Europe’s offshore wind future.”
At 260 metres tall, the gigantic turbines at Dogger Bank are almost twice the size of the London Eye and the same height as New York’s iconic Rockefeller Centre. The first power milestone marks the first of what will eventually be 277 turbines powered-up across the project. Each of these turbines will be progressively commissioned between now and full commercial operation in 2026. When complete, Dogger Bank will be the world’s largest offshore wind farm, more than two and a half times the size of the largest offshore wind farm currently in operation^.
Dogger Bank sits 70 nautical miles (130km) off the coast of Yorkshire and will occupy an area almost as large as Greater London and nearly twice the size of New York City.
World-firsts in supply chain delivery
The Dogger Bank project has delivered several world-firsts in supply chain delivery that will significantly accelerate the speed at which future offshore projects can be developed. The precision offshore installation of GE Vernova’s new 13MW Haliade-X turbine technology at Dogger Bank A was completed by expert technicians and engineers working off Jan De Nul Group‘s newest jack-up installation vessel, Voltaire. With a lifting capacity of 3,200 tonnes, the Voltaire is the largest offshore jack-up installation vessel of her kind in the world and the first ultra-low emissions ship of its kind.
Dogger Bank also marks the first use of HVDC transmission technology to connect a British wind farm to National Grid’s UK energy network. This includes the installation of the world’s first unmanned offshore HVDC substation platform at the site, as well as first use of Hitachi Energy’s HVDC Light® transmission system which was successfully executed in record time of 38 months with the highest safety and quality standards.
GE Vernova Offshore Wind CEO Jan Kjaersgaard said:
“We are delighted to have energised the first Haliade-X turbine at sea as part of the Dogger Bank Wind Farm, and we want to congratulate our customers and thank all of our partners on achieving this important milestone. At GE Vernova we are committed to electrifying the world while simultaneously working to decarbonize it. We are honored to have been able to provide the first of a next generation of 13MW+ turbines for this historic project, reinforcing the critical role of technology innovation in meeting the challenges of climate change.”
Jan Van Impe, Manager Jan De Nul Offshore Renewables at Jan De Nul Group, added:
“Our Voltaire has proven today that the scale and characteristics of the offshore Dogger Bank turbines offer the perfect challenge for this next generation state-of-the art jack-up installation vessel. We are excited to have installed the very first offshore GE Haliade-X turbine on the Dogger Bank Wind Farm in a sustainable and efficient way, and we are looking forward to continuing this mission with industry leaders SSE Renewables, Equinor and Vårgrønn to further construct the energy transition for the UK energy market.”
Claudio Facchin, Chief Executive Officer, Hitachi Energy, said:
“The urgent energy transition requires strong collaboration, new business models, and global standards. We are proud to be the technology partner for the Dogger Bank Wind Farm project, with HVDC being the force multiplier for the clean energy transition, increasing access to an energy system that is more sustainable, flexible and secure. Today is a significant milestone in securing the UK’s future energy needs, made possible by foresighted partners such as SSE, Equinor and Vårgrønn, that have made the UK a leader in the transition to clean power.”
John Twomey, director of customer connections at National Grid, said:
“It’s a momentous engineering achievement and landmark moment to see Dogger Bank exporting its first power onto the grid. When operational as the world’s biggest wind farm, its turbines will play a key role supplying Britain with green, homegrown energy. We’re proud to have played our part reinforcing our Creyke Beck substation in readiness to safely connect that clean power to our network, and on to homes and businesses around the country.”
Creating local jobs
More than 2,000 UK jobs have been created or supported in relation to the construction and operation activities of Dogger Bank. Many of these are based in the north of England, where the project’s supply chain is creating long-term opportunities for people just starting out in their careers, as well as more experienced workers transitioning from other industries to renewable energy.
RenewableUK’s Chief Executive Dan McGrail said:
“The sheer scale of Dogger Bank shows that offshore wind is taking centre stage in Britain’s clean energy system as we move away from expensive imported fossil fuels to secure cheap homegrown power.
“This massive innovative clean energy project is a significant step forward for the UK’s world-leading offshore wind industry, creating thousands of jobs and attracting billions in private investment.
“Coastal communities in the north of England and beyond are benefitting from the new industrial opportunities which offshore wind is providing. This shows that the Government is right to press ahead with policies to increase our energy security by ensuring that vital new clean energy projects can be built faster”.
Ends
Further information from:
Jake Hamilton, Communications Officer, SSE Renewables
M: 07342026875 / jacob.hamilton@sse.com
** Photos and B-roll footage **:
See Dropbox and Vimeo link below to photos and B-roll footage of the first turbines installed at Dogger Bank site in the North Sea:
https://www.dropbox.com/sh/1ehg835tf5x4yu8/AAB3zUDd9YDULXlptnpdwC0wa?dl=0
https://vimeo.com/872539585/33eaf222ad?share=copy
** Please credit: Dogger Bank Wind Farm **
* 6 million homes powered per annum based on Typical Domestic Consumption Values in Britain (Medium Electricity Profile Class 1, 2,900kWh per household; OFGEM, January 2021), typical 55% offshore wind load factor, and projected installed capacity of 3.6GW.
21st August 2023 in Community News, Press releases
- 62 scholarships are available during the construction of the wind farm, for students in these communities studying science, technology, engineering and maths subjects to support the cost of further education.
- The programme is open to students in South Tyneside, Redcar and Cleveland and East Riding of Yorkshire.
- The scholarship fund will support students undertaking courses focussed on science, technology, engineering and maths (STEM) courses, to help young people prepare for working life in a net zero world.
Students from coastal communities in the north and north-east of England are reminded that the third year scholarship fund closes for applications in less than two weeks.
Dogger Bank Wind Farm’s Scholarship Fund provides grants of £5,000 to local students undertaking science, technology, engineering and maths (STEM) courses in further education, with a total of 62 scholarships being awarded during the world’s largest wind farm’s construction phase.
The scholarship fund focuses on the areas of East Riding of Yorkshire, and Redcar and Cleveland, where the windfarm connects to the National Grid, as well as South Tyneside, where the Operation and Maintenance Base will be located.
Students should take note they only have until 1 September 2023 to apply for this year’s round of support. Further details and how to apply can be found at https://doggerbank.com/about/community/.
Oliver Cass, Project Director from Dogger Bank Wind Farm said
“The third round of the scholarship fund has once again proven very popular, it’s great to see the quality of applicants remains high and we encourage local students to make their application before the closing date next month. As we build the world’s largest offshore wind farm, we’re proud to continue supporting young people at a key stage in their educations and preparing for working life in a net zero world.”
Dogger Bank has already awarded 50 scholarships to date to local students undertaking science, technology, engineering, and maths (STEM) courses in further education to help young people prepare for working life in a net zero world and support students with tuition fees at a key stage in their educations.
Dogger Bank Wind Farm will be located more than 130 km off the northeast coast and will generate enough renewable energy to power six million UK homes. A joint venture partnership between SSE Renewables (40%), Equinor (40%) and Vårgrønn (20%). The wind farm is being built in three consecutive 1.2 GW phases: Dogger Bank A, B and C – connecting to the National Grid in both East Riding of Yorkshire and on Teesside.
SSE Renewables is leading on the development and construction of Dogger Bank Wind Farm, and Equinor will operate the wind farm on completion for its expected operational life of around 35 years.
In June 2021, Dogger Bank Wind Farm unveiled plans for a £1 million construction fund to support coastal communities where its onshore infrastructure is being developed. The programme includes a significant investment in science, technology, engineering, and maths, as well as an operators fund to support local causes. Further information is available at www.doggerbank.com/about/community/
Further details on the scholarship fund and community investment from Dogger Bank can be found here.
Ends
Picture caption: The scholarship fund will support students studying science, technology, engineering, and maths, to help prepare them for the highly skilled jobs in a net zero world.
9th August 2023 in Press releases, Supply Chain
Intasite, a leading provider of innovative workplace safety solutions for high hazard industries, has been contracted by Equinor to create health and safety induction content for its operations and maintenance (O&M) base at Port of Tyne, South Shields.
In a unique element of the partnership, the customised induction content also includes videos featuring the children of the employees of the world’s largest offshore windfarm in health and safety and induction videos. This approach is intended to make the health and safety information more memorable and impactful.
The Dogger Bank Wind Farm currently under construction 130km off the North East coastline, will become the world’s largest offshore wind farm once complete in 2026. Dogger Bank’s O&M base has been constructed in the Tyne Dock Enterprise Park (TDEP) as part of the Port of Tyne’s Tyne Clean Energy Park.
Intasite’s collaboration with Dogger Bank Wind Farm adds to its growing presence in the renewable energy sector, following its partnership with SeAH Wind. The company has been actively working with various renewable organisations, including SSE Renewables, EDF Renewables, Hitachi Energy, SeAH Wind, and RWE, to develop safety induction processes and create safer working environments.
By using the Stockton-based business’s platform, companies can streamline the induction process and provide comprehensive and interactive safety modules that can be completed by visitors, staff, and contractors from any desktop or mobile device. The platform also offers features such as contractor and supplier management, safety briefings, language translations, and integration with access control for enhanced security.
Intasite’s commitment to providing effective and user-friendly health and safety induction solutions has gained recognition in the UK industry. The company’s in-house production team specialises in creating health and safety induction videos, ensuring that the content is tailored to specific safety requirements and industry standards.
Digitising and streamlining the induction process with Intasite’s platform enables organisations to improve employee engagement and comprehension, reduce compliance risks, and foster a culture of safety from day one.
Danielle Croce, director at Intasite, said: “We are pleased that once again, we have confirmed Intasite as the induction provider of choice for the renewable energy sector.
“By featuring employee’s children in the videos, this will make the health and safety information more memorable and impactful.”
David Collier, Equinor SSU lead for Dogger Bank, said: “At Dogger Bank, health and safety is our top priority. By utilising Intasite’s platform, we have successfully incorporated captivating content to the induction process, being able to include the children of our own employees. By connecting our team through their loved ones, we achieve not only heightened engagement but also a greater commitment to maintaining a safe and secure work environment.”