Dogger Bank Wind Farm confirms next round of convertor station transformer deliveries 

11th May 2023 in Operations, Project news, Supply Chain

Dogger Bank Wind Farm’s tier one contractor Hitachi Energy is currently scheduled to begin transporting the latest electricity transformers, for the project’s second phase Dogger Bank B, from Hull to the project’s East Riding convertor station site near Cottingham from June 4.

Like last year’s deliveries during the project’s first phase, the transformers will travel from Albert Dock, Hull via the A63, A1034 and the A1079. The size of the transformers requires the use of abnormal load vehicles. There will be four deliveries anticipated on the mornings of 4 June and 11, 18 and June, with each delivery taking between 6-8 hours, dependent on the conditions. Further updates will be provided by the project as necessary

Rachel Lawrence, Community Engagement Manager for Dogger Bank Wind Farm, said:

“We were extremely grateful for the patience of communities in this area during our first round of deliveries last year and while our contractor will again do everything it can to minimise disruption during these latest deliveries, it is possible some journey times may be slightly longer than normal, and we would ask the public for their understanding as we carry out this critical work.”

The transformers will be delivered on specialist girder frame trailers provided by UK firm Allelys. The trucks will be around 70 metres long and 5 metres wide and will travel at approximately 10 -15 miles per hour. To support the delivery the team has worked with contractors and local highway officials from East Riding of Yorkshire Council to carefully plan the route and minimise disruption to road users.

The specialist girder frame trailer will have a police escort to help manage traffic and make the process as smooth and safe as possible. Along the route, there may be a pause from time to time as the specialist trailer lowers its suspension to safely pass under bridges.

Overview of the route:

The delivery convoy consisting of the abnormal load vehicle, police and support vehicles will leave the Albert Dock in Hull and make its way westbound, along the A63 to join the A1034 at South Cave heading north. The convoy will then join the A1079 at Market Weighton, heading east until the outskirts of Beverley, where the vehicle will turn south remaining on the A1079 and is expected to arrive at the convertor station site entrance, located between Beverley and Cottingham in the afternoon on the specified dates.

The transformers will play an integral role in the operation of two onshore convertor stations in East Riding of Yorkshire that are currently under construction at the A1079 site between Beverley and Cottingham. Eventually they will convert the current from the wind farm for transmission via the national grid network to millions of UK homes after the renewable energy has made its way under the ground from the landfall point at Ulrome, between Bridlington and Hornsea.

ENDS

Picture caption: Allelys will deliver transformers to the Dogger Bank Wind Farm convertor station site.