Latest news

UK civil engineering company extends its work on Dogger Bank Wind Farm with new contract

11th June 2021 in Press releases, Project news, Supply Chain

Jones Bros Civil Engineering UK has been appointed to deliver the enabling works package for the onshore convertor station platforms for the third phase of Dogger Bank Wind Farm, in a joint contract with neighbouring Sofia Offshore Wind Farm.

Jones Bros has been engaged by RWE’s Sofia Offshore Wind Farm, to manage the works on behalf of both Sofia and Dogger Bank C to minimise disruption to those living or working near the site.

The Jones Bros works will include providing a level load-bearing stone platform for the converter stations; two new accesses to the site with associated bellmouths; welfare and laydown areas; drainage system, and associated utilities.

Dogger Bank Wind Farm is currently being developed in three 1.2GW phases: Dogger Bank A, B and C. Dogger Bank A and B is a joint venture between SSE Renewables (40 per cent), Equinor (40 per cent) and Eni (20 per cent), while Dogger Bank C is a 50:50 joint venture between SSE Renewables and Equinor.

Dogger Bank A and B will connect to the National Grid near Beverley in East Riding of Yorkshire, while Dogger Bank C will connect to the National Grid at Lackenby, on Teesside.

North Wales-based Jones Bros started work on the land-based infrastructure for the first two phases of Dogger Bank Wind Farm last year, and has recently increased its team to 90 as work ramps up in preparation for the installation of 80 miles of underground cables from Ulrome to the onshore convertor station near Beverley.

On Teesside, between 25 and 30 Jones Bros workers will be on the site at any one time on behalf of Sofia Offshore Wind Farm and Dogger Bank C, with completion scheduled for April 2022.

The new contract win for the civil engineering firm is also expected to deliver opportunities for apprenticeships in the north-east of England as well as for suppliers such as fencing, haulage and other materials.

Eryl Roberts, contracts director at Jones Bros, said:

“We’re very pleased to be continuing our relationship with SSE and Equinor, both of whom are involved with Dogger Bank A and B, and look forward to developing our relationship with RWE.

 “Both Sofia and Dogger Bank C are significant projects in their own right and will deliver 1.4GW and 1.2GW of renewable power respectively once complete.

 “As with all of our projects, we will look to provide opportunities locally in the supply chain as well as for apprentices.”

Work is now underway and is expected to take approximately 10 months to complete.

Dogger Bank Wind Farm Project Director, Steve Wilson, said:

“This is a great opportunity for us to extend our collaboration with UK-based Jones Bros, following the start on the first two phases of the wind farm in East Riding. We’re also delighted to be working with Sofia Wind Farm in an innovative way, to ensure the impact on the local community on Teesside is minimal.”

 Sofia Project Director Matthew Swanwick said:

“This is a unique and complex project given the close cooperation between two separate wind farm developers, to the point of sharing a contractor for the early onshore construction activity, and so we welcome being able to leverage the breadth of experience Jones Bros. has had on previous UK infrastructure projects.”